Product backlog column/type missing?

Mar 24, 2010 at 12:08 PM

Hi and thanks for a very great dashboard.

We have started to test it in our Conchango projects.

The column for PB has no information if the item is a Product backlog item or a BUG.

Havn't anyone else need to see the type of a row?

 

Ulf

P&L Nordic AB

 

Mar 30, 2010 at 11:21 PM

We prefix all our work items with either "PBI" or "BUG" in the title, so it hasn't been an issue for us...

Mar 31, 2010 at 6:09 AM

Yes, but the item type is already in the TFS, why type the same information manually???

Completely unneccesary work.

 

Apr 5, 2010 at 11:36 PM

What scenario do you have where you would want to know the difference in the Scrum Dashboard?

Apr 6, 2010 at 4:56 AM

The need to see if it is a bug och PBI is more or less every Sprint planning meeting. When chosing beteween PBI's and BUG's. If the BUG should be fixed next sprint or the sprint after.

Sometimes there are bugs that are very time consuming, maybe bigger than a PBI and we have been foold by the not done calculations several times since the product owen sometimes can't see the difference betweeen a bug and a new PBI.

 

Apr 7, 2010 at 9:05 AM
Edited Apr 7, 2010 at 9:05 AM

I noticed that impediments are shown with a litlle yellow warning sign.  Maybe a similar solution with another icon???

 

Apr 9, 2010 at 8:24 PM

Not a bad idea.  My suggestion would be to add a feature request on the issues tab.

In our case, we just let the Product Owner prioritize the PBIs and BUGs together, and then go from there.