Remaining Work Not updated

Apr 8, 2009 at 10:10 AM
Hi, 

I have noticed that PBI "remaining work" is not updating after I have installed the newest beta.  I'm not sure if my problem is connected to the update.  (In can force a update if I run the SyncAllWorkRemaining).

/Nicolas
Coordinator
Apr 20, 2009 at 3:55 PM

Hi,

make sure the TFS Scheduler service is running on the server.

/Per

 

Apr 22, 2009 at 11:26 AM
Hi

Just wanted to follow up, in case some-one was having the same problem: We look at everything, but ended up with reinstalling Scrum For Team System: http://scrumforteamsystem.com/cs/forums/2010/ShowPost.aspx#2010